New Homes Are Taking Form at Penybryn

Works are officially underway on the development of 24 dwellings at Hill Top Close, Whittington.

A mix of Vibro and Driven piling works have been undertaken to plots 1 to 22. The foundations to plots 2-8 have been dug and poured and the below ground substructures are complete in preparation for the beam and block.

The road drainage is complete and works are underway to the 2.6m retaining wall which is progressing well.

We are looking forward to seeing this site progress and continuing our working relationship with Shropshire Towns and Rural Housing.